DP Road Phase II Reconstruction Project Updates

DP Road.JPG

Construction activity for the week of June 17, 2024

TLC Plumbing & Utility is working Monday through Friday, 7 a.m. to 5 p.m.

Parking:

  • Parking will not be allowed south of DP Road outside of designated areas south of Ace Hardware and south of the Los Alamos Fire Training Academy.

Traffic Control:

  • Potholing to identify existing utilities along the south side of DP Road continues.
  • Crews will begin excavating and trenching to install new utility lines the week of June 20, 2024.
  • Follow all work zone signs and exercise caution; flaggers may direct traffic during certain construction events.
  • Access to businesses will be maintained; westbound traffic direction remains unchanged. 

All questions and concerns should be sent to the Public Works Department at lacpw@lacnm.us or call 505-662-8150. For additional project details, visit the Public Works Department DP Road Reconstruction Project.