Urban Trail Phase I & II Multi-use Trail Project

  • Project typeMulti-Use Trail
  • Project value$6,862,500
  • Project scheduleAll work associated with this contract will be complete by December 2024
  • Contractor nameHasse Contracting Company, Inc.
20231023-ProjectAreaMap-UrbanTrailPhase1&2.jpg
Project Scope

Urban Trail Phase I includes construction of a 10-foot-wide concrete multi-use trail 0.434 miles in length between the intersection of Trinity Drive and 20th Street, through the Fuller Lodge grounds to the intersection of Ponderosa Street and Spruce Street. Work will also include construction of curb and gutter, retaining wall, signage, striping, lighting, and a drainage structure. 

The scope of work includes work on Phase I and Phase II concurrently. 

Project Updates
Project Overview

Urban Trail Phase II includes construction of a 10-foot-wide concrete multi-use trail 0.46 miles in length between the intersection of Ponderosa Street and Spruce Street through the wooded area by the tennis courts and along Canyon Road to the rear entrance of the Aquatic Center. Work will also include construction of curb and gutter, drainage improvements, retaining walls, lighting, signage, striping, a rapid flashing beacon, and 370 linear feet of precast boardwalk.

View the video of the October 10, 2023 presentation to Council.

Download the October 10 presentation.(PDF, 3MB)

Download the Project Map.(PDF, 1MB) (JPG, 737KB)

This project supports two of Council's Strategic Goals; investing in infrastructure and enhancing communication. This project provides maintenance and improvements to existing infrastructure. The enhancement of communication strategic goal is being accomplished by engaging the public and coordinating citizen involvement and feedback as a key part of the project development process. 

Location

Trinity and 20th Street, Los Alamos,NM 87544  View Map