37th Street & Pinon Park Project: ADA Update and Renovations

Construction Timeline & Progress

What's Next? 

July 2024-Construction Begins

Check back for updates and construction progress. 

Project Timeline to Date

Aug 2023 - Staff Kick Off meeting

Sept 2023 - Initial Community Listening sessions for each playground. Meetings at Pinon and 37th street, Get additional feedback from the Youth Activity Centers and local schools.

Dec 2023 - Return with two options for review by user groups at on-site public meetings, meet in locations near the playgrounds.

Jan 2024 - Finalize designs - Parks and Recreation Advisory Board presentation.

Feb 2024 - RFP and Bid for playground renovation.

April 15, 2024 -Press Release Issued

April 2024 -Construction contract awarded

Scope of the Project

Playground renovation is the responsibility of the Parks and Open Space division. These playgrounds were identified as needing improvements to meet American with Disabilities Act accessibility requirements and as needing improvements based on the CSD Integrated Master Plan. The renovation will improve safety, access, and update amenities. In August 2023 the Community Service Department started the process with staff kick-off meetings, and Sept 2023, Initial Community Listening sessions for each playground began. Cory Styron, the Community Services Director gathered feedback from youth at local schools and Activity Centers. Based on input already received, there are two concepts that we would like your feedback on.

 

Community Meetings

April 20, 2024

  • 9:00 - 10:30 AM 37th Street Tot Lot (in person)
  • 11:00 - 12:30 AM Pinon Park (in person)
Documentation

Public Information & Involvement Plan (PIIP)

37th Street Play Lot Information 

Pinon Park Playground Information

Additional Documentation

Access All Project Materials

View the Full Project Document Folder
Contains meeting videos, design files, survey results, and community feedback.

 37th Street & Pinon Park Playlot Project Documents Folder