37th Street & Pinon Park Project: ADA Update and Renovations
Construction Timeline & Progress
What's Next?
August 1, 2025 - Pre-Construction meeting with County and LA Landscapes and More, LLC.
October 1, 2025 - Construction and staging begins by LA Landscape and More, LLC.
Check back for updates and construction progress.
Project Timeline to Date
August 8, 2023 - Staff Kick Off meeting.
September 23, 2023 - Initial Community Listening sessions.
- 37th Street Playlot, 9 AM-10:30 AM, concept posted at Mesa Public Library.
- Pinon Park Playlot, 11 AM-12 PM, concept posted at White Rock Library.
January- April 2024- Meetings held with schools to discuss design options and gather community input .
April 15, 2024 - Press Release for 37th and Pinon Playground Renovations: Survey and Public Feedback Event(PDF, 209KB)
April 20, 2024 - Public Meetings to introduce and review the playground projects.
- 37th Street Playlot, 9 AM-10:30 AM, concept posted at Mesa Public Library.
- Pinon Park Playlot, 11 AM-12 PM, concept posted at White Rock Library.
June 2, 2024 - Community survey results and draft final concept posted on projects page.
August, 8, 2024 - Final Draft Concept Presentation brought to the Parks and Recreation Board for support of playground renovation.
February 2025 - Developing IFB Proposal.
March 25, 2025 - Submitted IFB Request and Draft to Procurement
April 28 - June 10, 2025 - IFB for 37th Street and Pinon Playlots were advertised. Closed at 2 PM on June 10.
June 12, 2025 - Bid evaluation committee reviews bids and selected a contractor.
July 8, 2025 - County Council Approved the proposed budget for the bid received for the 37th Street and Pinon Playlot Project.
Scope of the Project
Playground renovation is the responsibility of the Parks and Open Space division. These playgrounds were identified as needing improvements to meet American with Disabilities Act accessibility requirements and as needing improvements based on the CSD Integrated Master Plan. The renovation will improve safety, access, and update amenities. In August 2023 the Community Service Department started the process with staff kick-off meetings, and Sept 2023, Initial Community Listening sessions for each playground began. Cory Styron, the Community Services Director gathered feedback from youth at local schools and Activity Centers. Based on input already received, there are two concepts that we would like your feedback on.
Community Meetings
April 20, 2024
- 9:00 - 10:30 AM 37th Street Tot Lot (in person)
- 11:00 - 12:30 AM Pinon Park (in person)
Documentation
Public Information & Involvement Plan (PIIP)
37th Street Play Lot Information
Pinon Park Playground Information
Additional Documentation
- 37th Activities Mountain Elementary(PDF, 306KB)
- 37th Color Board Mountain Elementary(PDF, 144KB)
- 37th Street Mountain Elementary Activities(PDF, 332KB)
- 37th Street Aspen School Activities(PDF, 327KB)
- 37th Street Aspen School(PDF, 124KB)
- 37th Street Youth Activity Center(PDF, 140KB)
- Pinon Park Amenities Youth Activity Center(PDF, 188KB)
- Pinon Park Youth Activity Center(PDF, 127KB)
- Pinon Pinon Elementary Amenities(PDF, 192KB)
- Pinon Pinon Elementary Colors(PDF, 127KB)
Access All Project Materials
View the Full Project Document Folder
Contains meeting videos, design files, survey results, and community feedback.
37th Street & Pinon Park Playlot Project Documents Folder