Tentative timeline for EOC grant applications and construction planning to align with 2025 goals:
Phase 1: Preliminary Planning and Stakeholder Engagement
January – February 2025
Identify and review available funding opportunities (e.g., FEMA Building Resilient Infrastructure and Communities (BRIC) grants, Homeland Security Grant Program (HSGP), state-specific grants).
Engage key stakeholders (local government, emergency services, community leaders) to define the scope and requirements for the EOC project.
Conduct a gap analysis to document the current limitations in emergency operations and justify the need for an EOC.
Draft letters of support from regional partners and potential mutual aid collaborators.
Key Deliverables:
Project justification documentation.
Stakeholder buy-in and partnership agreements.
Phase 2: EOC Design and Cost Estimation
March – May 2025
Hire or consult with an architectural or engineering firm to draft a conceptual design for the EOC.
Develop a preliminary budget estimate for construction, equipment, and technology.
Integrate ADA-compliant features and environmental considerations into the design.
Begin drafting the grant proposal, incorporating design plans, cost estimates, and expected community benefits.
Key Deliverables:
Conceptual EOC design and budget.
Draft grant proposal with supporting documentation.
Phase 3: Grant Submission and Advocacy
June – August 2025
Finalize and submit grant applications to FEMA and other identified funding sources.
Schedule follow-up meetings with grant officials to advocate for the project and answer questions.
Explore additional funding opportunities through local or regional economic development programs, private foundations, or corporate sponsors.
Key Deliverables:
Submission of all grant applications.
Advocacy meetings with funding agencies.
Phase 4: Grant Award and Pre-Construction Planning
September – December 2025
Respond to any follow-up requests from granting agencies regarding application details.
If grants are awarded, secure additional local matching funds as required by grant terms.
Conduct a formal procurement process to select contractors for EOC construction.
Develop a detailed construction timeline, incorporating risk mitigation strategies for delays.
Key Deliverables:
Receipt of grant awards.
Contracts signed with construction and technology vendors.
Detailed construction plan finalized.
Phase 5: EOC Construction and Implementation
2026 and Beyond
Begin site preparation and construction based on finalized plans.
Procure and install technology and equipment as construction progresses.
Conduct ongoing inspections to ensure project stays on schedule and within budget.
Host a ribbon-cutting ceremony and public tours upon project completion.
Milestones Overview for 2025
Milestone
|
Deadline
|
Complete stakeholder meetings
|
February 2025
|
Finalize EOC design & budget
|
May 2025
|
Submit grant applications
|
June – August 2025
|
Secure funding awards
|
September 2025
|
Initiate contractor selection
|
December 2025
|