Townsite 14” Pipeline Replacement – Phase 1

  • Project value$ 2,883,500
  • Project scheduleSummer 2026
Road with cars

DPU will oversee replacement of approximately 6,700 linear feet of 14" steel pipe installed in 1949 with a new 14" ductile iron pipe along NM-502. The existing 14" steel pipe is aged and deteriorated and experiences regular leaks. This line is a critical transmission line that conveys water from Otowi Well #4 to the Townsite area of Los Alamos.

 

 

 

Budget:            Water Trust Board                                          $ 2,500,000

                        CIP                                                                 $ 383,500

                        Total                                                               $ 2,883,500

 

Contact details

Customer Care Center
(505) 662-8333