North Mesa & North Community Pavement Preservation Project

  • Project typeNorth Mesa & North Community Pavement Preservation Project
  • Project value$2,250,066
  • Project scheduleSeptember - October 2025
  • Contractor nameAlbuquerque Asphalt Inc.

Phase One - North Community - September 29 - October 8

 Phase 1.jpg

Hours of operation:  7:00am to 7:00pm

Lane Closures: East bound lanes of Diamond Dr reduced to a single lane during hours of operation.

Restrictions: Residents are asked to remove all vehicles and refrain from street parking during hours of operation on the following streets and days listed below.

Milling Operations:

39th Street: September 29 and 30

37th Street: October 1 and 2

36th Street: October 6 and 7

35th Street: October 7 and 8

Paving Operations:

39th Street –TBD

37th Street –TBD

36th Street –TBD

35th Street –TBD

Phase Two - North Mesa - San Ildefonso Road from the intersection of North Mesa Rd. east and including Stoneview Dr. 

San Ildefonso Road East Bound

San Ildefonso Road West Bound

Stoneview Drive

**Check back for updates.

Phase Three - North Mesa Road from the roundabout to San Ildefonso Rd. and the Hawks Landing Subdivision

North Mesa East Bound

North Mesa West bound

Deer Trail

Deer Court

Terry Lane

Mendius Lane

**Check back for updates. 