Los Alamos Wastewater Treatment Plant Improvements
- Project value$2,000,000
- Project scheduleConstruction 2026
The Los Alamos Wastewater Treatment Plant was commissioned in 2004 and has been in operation for 20 years. The equipment at the plant has maintenance issues and is nearing its life expectancy. With several items needing to be addressed, DPU will apply for a $2,000,000 Rural Infrastructure Program (RIP) loan to fund these projects together.
Budget: Aeration Basin Crack Repair $800,000
Motor Controls Centers – Miscellaneous $200,000
Fine Screen $500,000
Blower Building HVAC $200,000
UV Disinfection Replacement $300,000