Start of construction - February 2, 2026
- Project typeDenver Steels Phase II Improvements Project
- Project value$7,573,640.00
- Project scheduleFinal Completion - August 28, 2026
- Contractor nameTLC Plumbing & Utility
- Completion DateAugust 31, 2026
The Los Alamos County Public Works Department, in partnership with the Department of Public Utilities and under contract with Spear D Construction (TLC Company Inc.) announces that the Denver Steels Phase II Improvement Project will begin on Monday, February 2, 2026.
The project includes replacement of roadway, targeted concrete replacement including curb and gutter, valley gutters, sidewalk, drive pads, and ADA improvements. Aging water lines and fire hydrants will also be replaced.
During construction, road closures, lane restrictions, and detours will be in place. Residential access will be maintained.
Construction work will occur from 7:00 a.m. to 6:00 p.m., Monday through Friday. To minimize disruption, the contractor will notify and coordinate with affected residents for certain construction logistics, utility upgrades, and traffic changes as work progresses. Mail delivery, trash and recycling services, school bus routes, public transit, and emergency vehicle access will not be interrupted.
The County appreciates the community’s patience and cooperation during construction.
For questions or more information, please contact the Public Works Department at 505-662-8150 or Department of Utilities at 505-662-8333.
Location
Questa Street, Los Alamos, NM 87544 View Map
35.8800364,-106.3031138
Questa Street ,
Los Alamos, NM 87544
Questa Street ,
Los Alamos, NM 87544
Denver Steels Phase II Improvements Project