Public Works Projects
Contact Info

North Mesa Road Improvements Phase 2

Los Alamos County Project Manager: Juan Rael

Contractor: Star Paving, Inc.

Contractor Project Manager: David Espinosa

Update for week on July 16:

Star Paving will begin demolition work on sidewalk and driveways on Camino Mora and one on Camino Cereza. After the old concrete has been removed, trenching will begin for electrical conduit within these isolated areas. 

After the conduit is installed,k it will be back-filled, compacted, and formed for the new concrete placement. Please use caution around the heavy equipment and removal areas. 

Background Information:

Project area: Camino Mora, Camino Cereza, and Camino Manzana. 

Project consists of: Roadway rehabilitation- removal of surfacing, complete asphalt overlay, manhole adjustments, intermittent curb and gutter, sidewalks, drive pad replacement, landscape remediation and rigid electrical conduit installation. 

North Mesa Road Improvements Project Cumbres Del Sol Subdivision, Phase 2 will begin July 5, 2018.  

Initial activities will be mobilizing crews & equipment, clearing and grubbing, videotape documentation of current conditions before removal work begins.

Work hours will be Monday through Friday, 7:00 am to 5:00 pm. 

Access to residences as well as services such as mail delivery, emergency services, trash and recycling collection will be maintained.

Once additional schedule dates are confirmed, we will post them to this page. Please check back often. 

Please feel free to contact us with questions, concerns, or just to let us know how we're doing!.

DP Road Infrastructure

DP Road Infrastructure

Infrastructure for the A-16 A Site needs to be installed first on DP Road as part of the project (funding for the water,  gas, sewer lines and electric lines is a separate economic development project).

Click here to view a map of the proposed infrastructure on DP Road that will serve A-8 A, A-8 B, and A-9 and will terminate at A-16. 

Golf Course Improvements Project

County staff working with the Parks and Rec Board devise a plan that implements the Capital Improvement Projects (CIP) Golf Course Improvements at a cost not to exceed $4.524 million and implement it over a multi-year period. 

The main goal of the Golf Course Project is to replace the irrigation system. All other elements will be prioritized and determined throughout the project. 

Preliminary Project Development Schedule:
Design - February 2018 - September 2018
Construction - September 2018 - March 2020

Mesa Public Library Heating, Ventilation, Air Conditioning, and Lighting Improvements

Renovations for Library Heating, Ventilation, Air Conditioning, and Lighting Improvements will start late July.

Wayne Kohlrust: Project Manager
 

Improvements to the library include:

   * lighting upgrades to LED

   * changing ceiling spaces lower and upper levels for better airflow

   * replacement of the heating boiler

   * tinting of the skylight in reference area

   * replacement of the main air handling system

   * change from evaporative cooling system to refrigerated system

   * new digital control system for new HVAC system

   * professionally cleaning of ductwork

These improvements are all designed to improve the comfort of the patrons and staff, and better control the interior environment while reducing energy costs.

The library will re-open early December. 

We appreciate your patience.

Please feel free to contact us with questions, or concerns.

Please click here to visit the Mesa Public Library website for service information. 

Pinon Splash Pad

County staff working with the Parks and Rec Board devise a plan that proposes a splash pad in White Rock at a cost not to exceed $720,000 with a request to lower that if at all possible. 

During the design and construction phases the team will consider all cost saving elements including the type of operating systems to provide the best product for the lowest cost. 

Preliminary Project Development Schedule:
Design - January 2018 - May 2018
Construction - May 2018 - November 2018

Ice Rink Improvements

County staff working with Parks and Rec Board devise a plan that proposes improvements to the existing outdoor ice skating rink for an amount approximately $1.2 million which will include a shade study.

Preliminary Project Development Schedule:
Shade study - December 2017 
Design - June 2018 - May 2019
Construction - June 2019 - October 2019

Kiddie Pool - (Adjacent to Aquatic Center)

The new $6.5 million Kiddie Pool with low entry zone, splash features, lazy river and slide. It will be built using County land on the eastern grassy slope of the existing center with access provided from the main center. Design will get underway in spring 2018.

The Kiddie Pool will not be authorized to move ahead to construction until the LANL operations and maintenance contract is awarded (expected April/May 2018).

Kiddie Pool