spacer
Skip navigation links
News
Business
Community
Government
Services
Visitors
Skip navigation links
Capital Projects
Justice Center
Demolition of Trinity Site Buildings
Golf Course Community Building
New Municipal Building
Los Alamos Archival & Records Center Project
White Rock Visitor Center Complex
Community Development Projects
Council Projects
Economic Development Projects
Environmental Services Projects
Parks and Recreation Projects
Public Utilities Projects
Public Works Projects
Completed Projects
Justice Center  
Home > County Projects > Capital Projects > Justice Center

News and Updates as of July 29, 2010:

Grand Opening Set for August 26th!

Please join the County Council to celebrate the grand opening of the Justice Center at 10 a.m. on Thursday, August 26. The agenda includes raising of a new flag on the new flagpole near the front entrance, dedication of a special plaque outside the building, followed by refreshments and then public tours.

Justice Center

Updates

The eastern side of Oppenheimer has re-opened in the last week. 

Exterior signage has been ordered. Landscaping and contractor completion of any final close out items to wrap up construction are underway.

Project Description:

The Justice Center was built within a budget of $20,188,000. It was designed for meeting the requirements of County Resolution 06-18 for environmental sustainability. It meets the standards of a LEED 2.2 “Silver” rating.

The Justice Center includes: 

New Jail

Most of the single-story new addition on the western side of the property (on the Oppenheimer Drive side) was built for the housing of prisoners and detention support functions. New code compliant jail cells and detention support facilities were constructed. The design allowed for jail cell and day room areas to be expanded if needed - a second story could be added.

Renovation of the existing Police-Jail building

The existing single-story Police-Jail building was entirely gutted. New mechanical, plumbing, electrical, data and IT functions were added. Most of the Police administrative functions were placed in the renovated space. The Sheriff's office is located in this building. The two additions were attached to the west and east sides of the existing building.  

New Courthouse

The Municipal Court, Municipal Clerk and administrative functions are located on the first floor, along with a Hearing Room. The Magistrate and District Courts, as well as the court clerk and administrative functions, are located on the second floor.  

Contractor: HB Construction Inc. (Albuquerque, NM)

Design Consultant:  WH Pacific (Albuquerque, NM)

NOTE: This will be the last update to the webpage. This webpage will be archived following the grand opening on August 26.

 

 