Public Works Projects
Contact Info

North Mesa Road Improvements Phase 2

Update for week of August 6th:

Star Paving is scheduled to finish concrete work on Camino Mora, Camino Cereza and Camino Manzana this week. The crews will then transition into the asphalt removal.

Please continue to use caution around the heavy equipment and removal areas. You may notice 5-gallon buckets or coolers that contain concrete cylinder samples, please avoid these so as not to disturb the concrete material samples.

Look Ahead Schedule

Roadway milling is planned to start on August 13th on Camino Mora and Camino Cereza. There will be a large milling machine along with heavy equipment that will be loading the milling material.

If possible, please do not park on the street during this activity.

Thank you for your continued patience.

Background Information:

Project area: Camino Mora, Camino Cereza, and Camino Manzana. 

Project consists of: Roadway rehabilitation- removal of surfacing, complete asphalt overlay, manhole adjustments, intermittent curb and gutter, sidewalks, drive pad replacement, landscape remediation and rigid electrical conduit installation. 

North Mesa Road Improvements Project Cumbres Del Sol Subdivision, Phase 2 will begin July 5, 2018.  

Work hours will be Monday through Friday, 7:00 am to 5:00 pm.

Access to residences as well as services such as mail delivery, emergency services, trash and recycling collection will be maintained. 

Once additional schedule dates are confirmed, we will post them to this page. Please check back often. 

Please feel free to contact us with questions, concerns, or just to let us know how we're doing!.

Canyon Rim Trail Phase 3 Design

Fire Station 3 Bunkroom and Roof Improvements

Fire Station 3 was opened in 2008 and was constructed with an overhead air conditioning and radiant floor heating system.  Over time, fire department staff have noted that these separate systems compete and do not maintain adequate comfort levels.  

Improvements for Fire State 3 will include:

  • Modification of HVAC System
  • Removal and replace of drop ceiling in bunkrooms
  • Add thermostats to bunkrooms
  • Add Exterior Insulation Finish System to exterior bunkroom walls
  • Replace windows in bunkroom
  • Replace the Thermoplastic Polyolefin roof system over the living areas
  • Remove the equipment screen and replace with a railing system.
  • Add low voltage heating loops on the metal roof and inside new gutters and downspouts.

Work is expected to begin in September 2018 and Final Completion March 2019.

Project Manager: Harold Anthony Strain


Mesa Public Library Heating, Ventilation, Air Conditioning, and Lighting Improvements

Renovations for Library Heating, Ventilation, Air Conditioning, and Lighting Improvements will start late July.

Wayne Kohlrust: Project Manager 

Improvements to the library include:

   * lighting upgrades to LED

   * changing ceiling spaces lower and upper levels for better airflow

   * replacement of the heating boiler

   * tinting of the skylight in reference area

   * replacement of the main air handling system

   * change from evaporative cooling system to refrigerated system

   * new digital control system for new HVAC system

   * professionally cleaning of ductwork

These improvements are all designed to improve the comfort of the patrons and staff, and better control the interior environment while reducing energy costs.

The library will re-open early December. 

We appreciate your patience.

Please feel free to contact us with questions, or concerns.

Please click here to visit the Mesa Public Library website for service information. 

 

Canyon Rim Trail Underpass Design Phase

The Canyon Rim Trail Underpass will connect the trailhead on the south side of NM 502 to Camino Entrada on the north side with a concrete box structure beneath NM 502.

Wilson & Company will provide trail improvements, underpass selection, traffic control phasing and cost estimates for the Canyon Rim Trail Underpass design. Final design is estimated for September 2018.

Please feel free to contact us with questions, or concerns.

Capital Projects on Hold Awaiting Funding

Golf Course Improvements:

County staff working with the Parks and Rec Board devise a plan that implements the Capital Improvement Projects (CIP) Golf Course Improvements at a cost not to exceed $4.524 million and implement it over a multi-year period. 

The main goal of the Golf Course Project is to replace the irrigation system. All other elements will be prioritized and determined throughout the project. 

Preliminary Project Development Schedule:
Design - February 2018 - September 2018
Construction - September 2018 - March 2020


Ice Rink Improvements:

County staff working with Parks and Rec Board devise a plan that proposes improvements to the existing outdoor ice skating rink for an amount approximately $1.2 million which will include a shade study.

Preliminary Project Development Schedule:
Shade study - December 2017 
Design - June 2018 - May 2019
Construction - June 2019 - October 2019


Kiddie Pool - (Adjacent to Aquatic Center):

The new $6.5 million Kiddie Pool with low entry zone, splash features, lazy river and slide. It will be built using County land on the eastern grassy slope of the existing center with access provided from the main center. Design will get underway in spring 2018. 

The Kiddie Pool will not be authorized to move ahead to construction until the LANL operations and maintenance contract is awarded (expected April/May 2018).


Pinon Splash Pad:

County staff working with the Parks and Rec Board devise a plan that proposes a splash pad in White Rock at a cost not to exceed $720,000 with a request to lower that if at all possible. 

During the design and construction phases the team will consider all cost saving elements including the type of operating systems to provide the best product for the lowest cost. 

Preliminary Project Development Schedule:
Design - January 2018 - May 2018
Construction - May 2018 - November 2018

 

DP Road Infrastructure

DP Road Infrastructure

Infrastructure for the A-16 A Site needs to be installed first on DP Road as part of the project (funding for the water,  gas, sewer lines and electric lines is a separate economic development project).

Click here to view a map of the proposed infrastructure on DP Road that will serve A-8 A, A-8 B, and A-9 and will terminate at A-16.